13th span of Padma Bridge installed

4 || risingbd.com

Published: 06:18, 25 May 2019   Update: 15:18, 26 July 2020
13th span of Padma Bridge installed

Munshiganj Correspondent: The 13th span of the 6.15-kilometre long Padma Multipurpose Bridge was installed at Mawa point on Saturday morning.

A 150-meter long ‘3-B’ span has been installed on the 14 and 15 pillars at 10:25am, making 1,950-meter of the main structure of this mega bridge visible.

Deputy Assistant Engineer of Padma Bridge Project Humayun Kabir said with the installation of 13th span today, a total of 1,950 meters of the bridge became visible.

A total of 41 spans will be installed on 42 concrete pillars of the bridge, he said.

According to the project details, the construction of the 6.15-kilometre long Padma Bridge is going on in full swing with target to complete it as soon as possible.

The first span of the Padma Bridge was installed on September 30, 2017. The second span was installed four months later on January 28, 2018 while the third one was placed on March 11, after one and a half months.


risingbd/ Munshiganj/May 25, 2019/Ratan/Mukul

 